Capital investment of c.£10m
• Disinvestment
• Demolition
• Reverse Engineering
• New Process Equipment
• New System Services
• New Wet End of the Machine
• New Control System
• New Electrical Distribution
The project was to upgrade a 1980’s paper machine to increase output and increase in product range. Areas of disinvestment and demolition was carried out in a manner to minimise the manufacturing disruption to the clients site, the existing control system was reversed engineered, designing of multiple systems to work together as one.